KSA PPPs: Overview of Typical Structure and Stakeholders

How public-private partnerships are typically structured in Saudi Arabia, how PPP projects are procured and governed, and the role of each stakeholder.

14 September 2025·3 min read
On this page

    Typical PPP Structure

    Typical PPP structureDiagram of a typical PPP structure: government, concession agreement, project company (SPV), construction contract, independent engineer or reviewer, lender, contractor, operator, investor, and toll revenue or government payments.GovernmentConcession agreementProject company- (SPV) -Toll revenue /government paymentsConstructionContractIndependentengineer / reviewerLenderContractorOperatorInvestorDebtServiceDividends

    SPV Formation & Regulatory Compliance

    SPV Incorporated in KSA under Companies Law; must be 100% local or a joint-venture with ≥25% Saudi ownership under the Investment Law.

    SPV shareholders sign a Shareholders’ Agreement defining equity, governance, dividend policy, transfer restrictions.

    Concession Agreement

    Between Line Ministry (Contracting Authority) Sets term (25-30 yrs.), output specs, KPIs, handback standards, termination rights

    Service/Off-Take Agreement

    If no user fees: government pays periodic availability payments linked to performance metrics. If user fees: SPV collects tolls/charges under a regulated tariff framework

    Finance & Security Package

    Debt providers (banks, Sukuk investors) fund ~70-80% of capex.

    Direct Agreements: Lenders’ Direct Agreement: Lenders may replace SPV or contractors if SPV defaults—ensuring continuity

    Back-to-Back Subcontracts

    O&M Contract

    Long-term maintenance & operation obligations, with payment deductions for KPI shortfalls (uptime <58%)

    Financiers’ Engineer

    Appointed by lenders to monitor construction progress, certify milestones, and authorize drawdowns

    Independent Reviewer

    Sometimes an independent reviewer guarantees acceptance test, though excessive use can dilute risk

    Payment & Handover Flow

    Construction: SPV draws on debt/equity to pay EPC; government makes no payments. Operational: handover - KPI tests availability/user payments begin

    Procurement Process

    Pre-Feasibility Referral Any PPP ≥ SAR 200 m or Divestment ≥ SAR 50 m

    Submit to NCP Viability Study (60 days)

    Business-Case "Four Files"

    PartialRisk & Market Assessment
    Pre-FeasibilityScope, Structure, Cash Flow Model
    FullTechnical, Legal, Financial Due Diligence
    FinalContracts, Financing Plan, Guarantees

    Award Routes

    • Public Competition (default)
    • Limited Tender
    • Direct Award (Special Strategic Cases)
    • Unsolicited Proposals Study-Fee Reimbursed No Bid Premium; Auto-Qualify

    EOI- RFQ -> RFP Minimum Stand-Still Periods

    Stages of a PPP Project

    • Sector PSP Plan
    • Business Case Documents (Including Detailed Study of the PPP Project)
    • Tendering Plan
    • Tendering EOI Phase; Pre-Qualification Phase; RFP Phase
    • Award
    • Execution

    Stakeholder Map

    PPP stakeholder mapStakeholder map: Council of Ministers, CEDA and NCP at the top, linked to the Contracting Authority, Supervisory Committees and Ministry of Finance, with the EXPRO Authority and the Competition & Labour Authorities below.Council of MinistersCEDANCPContractingAuthoritySupervisoryCommitteesMinistryof FinanceEXPROAuthorityCompetition & LabourAuthorities

    Supervisory Committee Workflow

    • Supervisory Committees
    • Pipeline Governance
    • Business-Case Gate Approvals
    • Procurement Sign-Off
    • Inter-Agency Resolution

    Secretariat

    Other Stakeholders

    StakeholderRole in PPPKey Legal/Contractual Instruments
    Public Investment Fund (PIF)Project sponsor/co-investor (equity)
    Provider of sovereign support and guarantees
    Equity Subscription Agreement
    Government Support Agreement (if any)
    Direct Agreements with Lenders
    Ministry of Investment (MISA)Sectoral regulator issuing PPP tender guidelines
    Transaction Advisor appointment
    Engagement Letter
    Procurement/outreach reports
    Transaction AdviserManages the procurement process on behalf of MISA/PIF
    Drafts bid documents, evaluates proposals
    Engagement Letter
    Procurement/outreach reports
    Project Company (SPV)Implements the project: finance, design, build, operate
    Central contracting party to government and lenders
    Shareholders’ Agreement
    Financing Agreements (Debt/Equity)
    Sub-contracts (D&C; O&M)
    Lenders / Financial InvestorsProvide debt financing
    Monitor project performance via independent advisors
    Loan Agreements
    Direct Agreements (step-in rights)
    Security Documentation
    Contractor & O&M OperatorExecutes construction and operations under back-to-back subcontractsEPC (Design & Build) Contract
    Operations & Maintenance Contract
    Direct Agreements with SPV/Lenders
    Subcontractors & SuppliersDeliver specialist works and supply equipment
    Engaged under pay-when-paid and risk-pass-through subcontracts
    Subcontracts (back-to-back risk allocation)
    Direct/Consent Agreements for critical suppliers
    Independent Engineer / Technical AdvisorVerifies technical compliance and milestones on behalf of lenders (“Financier’s Engineer”)Appointment Letter
    Monitoring Reports to Lenders
    Independent Reviewer (Owner’s Engineer)Certifies key deliverables for the government (if mandated)Certification Reports
    Design Review Opinions
    Shariah AdvisorEnsures all financing and contracts comply with Islamic finance principlesShariah Certification Letters for Sukuk and financing documents