Since the entry into force of the Civil Transactions Law (“CTL”) in December 2023, Saudi courts have begun to articulate how contractually agreed damages, in accordance with article 178 CTL, are to be treated in commercial disputes.
Recent appellate-level judgments, read together with a growing body of first-instance decisions, suggest that courts are adopting a measured and structured approach that respects contractual autonomy while retaining judicial control to prevent excessive or unjust outcomes.
This note highlights the key trends that can be observed from recent case law.
1. Agreed Damages Are Enforceable in Principle
Courts have confirmed that contractually agreed damages are valid and enforceable under the CTL where they fall within the scope of article 178, namely, where the agreed compensation relates to a non-monetary obligation and reflects a genuine allocation of risk between the parties.
Where a contract specifies a fixed, clearly defined amount payable upon breach (such as early termination), courts have shown a willingness to enforce the agreed amount without requiring the claimant to separately prove actual loss. This reflects judicial acceptance that agreed damages serve a legitimate commercial function: providing certainty and avoiding disputes over quantification.
Courts have also focused on the correct characterisation of liquidated damages where non-payment is involved. Appellate guidance indicates that damages framed as compensation for early termination of a contract following breaches in payment obligations may be enforceable, whereas damages operating in substance as an increment on a monetary debt are unlikely to be upheld.
2. Agreed Damages Do Not Eliminate Evidential Burdens Entirely
While agreed damages reduce the need to prove quantum of loss, courts continue to require parties to establish that:
- The contractual trigger for the agreed damages has occurred;
- Any contractual preconditions (such as notices or cure periods) have been satisfied; and
- The breach is attributable to the party against whom the clause is invoked.
3. Judicial Power to Reduce Excessive Agreed Damages Is Actively Used
Courts have emphasised that Article 178 does not require blind enforcement of agreed damages.
Where an agreed amount is considered excessive in light of the circumstances, courts have exercised their statutory power to reduce the compensation, particularly where:
- A substantial portion of the contract has already been performed; or
- Enforcing the clause in full would place the non-breaching party in a better position than if the contract had been performed.
Key Takeaways for Contracting Parties
- Agreed damages remain a viable risk-allocation tool under Saudi law.
- Drafting should prioritise clarity, proportionality, and correct legal characterisation.
- Parties should anticipate judicial scrutiny, not automatic enforcement.
- Over-reliance on agreed damages as a substitute for proper evidence or contract management is risky.
Conclusion
The emerging judicial approach under the Civil Transactions Law reflects a balance between contractual freedom and judicial oversight. Courts are prepared to uphold agreed damages where they reflect a genuine and reasonable allocation of risk, but they will intervene where the amounts applied would produce disproportionate or unjust results.